Return to service study

Country:
Location:
Confidential
Fuel Type:
Energy From Waste

Key Challenges

To identify what works needed to be done to return this 22MW biomass site firing waste wood to return to generation after a lengthy period out of service.

RJM Solution

RJM’s engineers proposed to carry out a full review of every aspect of the plant’s operations, from materials handling, instrumentation review, baseline testing, fuel review, through to combustion and emissions. The study was broken up into five phases, over a compressed, 24 week period.

• Immediate Pre-Return to Service (RTS) works
• Secondary Pre-RTS works
• Return to Service
• Post-RTS Optimisation
• Improvement works.


    Australian flag
    AGL Bayswater, New South Wales

    Innovative NOx reduction solution

    Coal
    View Project
    Tanjung Bin 4, Johor

    Performance improvement project

    Coal
    View Project
    Northeast Utilities, Schiller Unit 6, New Hampshire

    NOx reduction project to meet Phase 1 RACT regulations

    Coal
    View Project
    Chalk Point 3 & 4, Maryland

    Burner modifications to reduce NOx and opacity

    Oil
    View Project
    Northeast Utilities, Norwalk Harbor

    Engineer, model and supply new NOx reduction system

    Oil
    View Project